*COMPLETE* Bldg. 35 - Basement, Chilled Water Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed Jun 20 09:52:56 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "oconaill@mit.edu" <oconaill@mit.edu>, "DICKP@MIT.EDU" <DICKP@mit.edu>,
        "alz@MIT.EDU" <alz@mit.edu>,
        OPS RM Campus Services Main <rm-mcs@mit.edu>,
        "icuevas@mit.edu" <icuevas@mit.edu>,
        "ktanaka@mit.edu" <ktanaka@mit.edu>, "jchun@MIT.EDU" <jchun@mit.edu>,
        "culpepper@mit.edu" <culpepper@mit.edu>,
        "davidrod@mit.edu" <davidrod@mit.edu>,
        "sbghosh@MIT.EDU" <sbghosh@mit.edu>,
        "herrickd@MIT.EDU" <herrickd@mit.edu>,
        "maxine@mit.edu" <maxine@mit.edu>, "bpant@mit.edu" <bpant@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "wayneb@mit.edu" <wayneb@mit.edu>,
        MIT Schedules Office <schedules@mit.edu>,
        "barnard@mit.edu" <barnard@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Ops RM Piping Systems Team
	<rm-pipesys@mit.edu>,
        "dbn@mit.edu" <dbn@mit.edu>, Ops RM Shutdown
	<rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support
 Staff" <cust-staff@mit.edu>,
        "lmp-all@mit.edu" <lmp-all@mit.edu>
CC: "mmcorrei@mit.edu" <mmcorrei@mit.edu>, "lstjohn@mit.edu" <lstjohn@mit.edu>
Date: Wed, 20 Jun 2012 09:52:43 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE85D4EE2@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

Good Morning -

This shutdown is complete as of 9:45am this morning.  The chilled water system is back in service.

Thank you,

Jani Findlay
Repair and Maintenance
X3-6381

-----Original Message-----
From: Janine Findlay 
Sent: Tuesday, June 19, 2012 10:56 AM
To: 'oconaill@mit.edu'; 'DICKP@MIT.EDU'; 'alz@MIT.EDU'; OPS RM Campus Services Main; 'icuevas@mit.edu'; 'ktanaka@mit.edu'; 'jchun@MIT.EDU'; 'culpepper@mit.edu'; 'davidrod@mit.edu'; 'sbghosh@MIT.EDU'; 'herrickd@MIT.EDU'; 'maxine@mit.edu'; 'bpant@mit.edu'; 'gillooly@MIT.EDU'; 'wayneb@mit.edu'; MIT Schedules Office; 'barnard@mit.edu'; 'monaglek@MIT.EDU'; 'shutdowns@mit.edu'; Ops RM Piping Systems Team; 'dbn@mit.edu'; 'rm-shutdown@mit.edu'; 'cp-command@mit.edu'; 'safety@mit.edu'; Operators; DOF Customer Service Center; Ops Custodial Admin & Support Staff
Cc: mmcorrei@mit.edu; lstjohn@mit.edu
Subject: Approved Bldg. 35 - Basement, Chilled Water Shutdown 

The following approved chilled water shutdown for Bldg. 35 - Basement, on Wednesday, June 20, 2012, 8:00am - 12:00pm, is for your information.  Any questions, please contact Larry St. John, x3-4948 and ask to have him paged.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: June 20, 2012
Day: Wednesday
Time: 8:00am - 12:00pm
Building(s): 35
Room(s): Basement
System: Chilled Water
Duration: 4 hours
Reason: 
to tie-in the chilled water line to the lab

Effect: 
Loss of chilled water for the duration of the shutdown.