[159403] in Hotline Meeting
Approved Bldg. 39 - All Labs, Low Temperature Lab Process Hot Water
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jun 12 14:25:11 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"domara@mit.edu"
<domara@mit.edu>, Jack Stark <jstark@plant.mit.edu>,
"burkhart@mtl.mit.edu"
<burkhart@mtl.mit.edu>,
"diadiuk@mit.edu" <diadiuk@mit.edu>,
"mcgrath@mtl.mit.edu" <mcgrath@mtl.mit.edu>,
"gillooly@MIT.EDU"
<gillooly@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU"
<monaglek@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"Ops RM
Plumbing Team" <rm-plumbing@mit.edu>,
Ops RM Piping Systems Team
<rm-pipesys@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "erita@mit.edu" <erita@mit.edu>, "mmcorrei@mit.edu" <mmcorrei@mit.edu>,
"rkwise@mit.edu" <rkwise@mit.edu>
Date: Tue, 12 Jun 2012 14:25:08 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE2B653DF@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved low temperature lab process hot water shutdown for Bldg. 39 - All Labs, on Saturday, June 16, 2012, 6:00am - 2:00pm, is for your information. Any questions, please contact Russell Wise, x3-4948 and ask to have him paged.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 16, 2012
Day: Saturday
Time: 6:00am - 2:00pm
Building(s): 39
Room(s): All Labs
System: Low Temperature Lab Process Hot Water
Duration: 8 hours
Reason:
to repair a leaking flange
Effect:
Loss of low temperature lab process hot water for the duration of the shutdown.