[159402] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Approved Bldg. 66 - Subbasement through 2nd Floor - Normal 480V

daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jun 12 14:16:50 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu"
	<whomeyer@mit.edu>,
        Ops RM Electrical Controls Team <rm-elecctl@mit.edu>,
        "rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu" <dcrovo@mit.edu>,
        "Ops
 RM Shutdown" <rm-shutdown@mit.edu>,
        "cp-command@mit.edu"
	<cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        Operators
	<Operators@plant.mit.edu>,
        "DOF Customer Service Center" <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
        "wdalzell@MIT.EDU" <wdalzell@mit.edu>,
        "hammond@MIT.EDU" <hammond@mit.edu>,
        "kfjensen@mit.edu" <kfjensen@mit.edu>,
        "alimart@mit.edu" <alimart@mit.edu>,
        "Swetzel@mit.edu" <Swetzel@mit.edu>,
        "OPS RM Campus Services East"
	<rm-ecs@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "wayneb@mit.edu" <wayneb@mit.edu>,
        MIT
 Schedules Office <schedules@mit.edu>,
        "barnard@mit.edu" <barnard@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>
CC: "koskae@mit.edu" <koskae@mit.edu>
Date: Tue, 12 Jun 2012 14:16:46 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE2B653D5@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved normal 480V building power (277v lighting; normal lighting only) shutdown for Bldg. 66 - Subbasement through 2nd Floor, on Monday, June 18, 2012, 5:00am - 6:00am, is for your information.  Any questions, please contact Billy Homeyer, x8-0432.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: June 18, 2012
Day: Monday
Time: 5:00am - 6:00am
Building(s): 66
Room(s): Subbasement through 2nd Floor
System: Normal 480V Building Power (277v lighting; normal lighting only)
Duration: 1 hour
Reason: 
We request a bldg 66-subbsmt, bsmt, 1st and 2nd floor normal 277V lighting shutdown from 5 AM to 6 AM on Monday morning, June 18th, 2012 for Crocker Electric (Chris Hamil 617-224-2492) to splice a 60A connection off the feeders cables for the 480V/277V lighting panel L-1, located in 66-117E, for temporary construction power required for the 66-125 Prof Tisdale renovation project by Elaine Construction (Nick Murray 617-799-7913). Evan Koska 4-6173 and Kim Sutherland 8-5962 are the MIT project managers.

Normal lighting on floors 66-SB, B, 1 and 2 will be the only thing affected.

Effect: 
Loss of normal 480V building power (277v lighting; normal lighting only) for the duration of the shutdown.