[158949] in Hotline Meeting
*Revised - Bldg.13-1st floor MBE lab,Fan Supply AHU6, Exhaust Fans
daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Thu May 24 08:43:10 2012
From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"Ops Custodial Admin &
Support Staff" <cust-staff@mit.edu>,
"jbartels@MIT.EDU" <jbartels@mit.edu>,
"mbulsara@mit.edu" <mbulsara@mit.edu>,
"jeileef@mit.edu" <jeileef@mit.edu>, "elk@MIT.EDU" <elk@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"jingkong@mit.edu" <jingkong@mit.edu>
CC: "shutdowns@mit.edu" <shutdowns@mit.edu>,
"mcweeney@mit.edu"
<mcweeney@mit.edu>,
Alan Legere <alegere@plant.mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>
Date: Thu, 24 May 2012 08:43:08 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE26DBC44@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
We have change the start time for this shutdown to begin at 6:00am on Friday, May 25, 2012 and end at 8:00am on Friday May 25, 2012.
Would you please let us know whether this does or does not have your approval.
Thank you,
Repair and Maintenance
Bernadette Drinkwater
x3-0938
-----Original Message-----
From: shutdown-response@MIT.EDU [mailto:shutdown-response@MIT.EDU]
Sent: Wednesday, May 23, 2012 2:00 PM
To: undisclosed_recipients@mit.edu
Cc: shutdowns@mit.edu; mcweeney@mit.edu; Alan Legere
Subject: Bldg.13-1st floor MBE lab,Fan Supply AHU6, Exhaust Fans EF15, EF16, EF17, EF18 shutdown request
Importance: High
The following Fan Supply AHU 6 and Exhaust Fans EF15, EF16, EF17, EF18 shutdown request for Bldg.13-1st flr, MBE lab on Friday, May 25, 2012 is for your information and response. Any questions, please contact Alan Legere x3-7636.
Would you please let us know whether this does or does not have your approval.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
X3-0938
Type: Normal
Date: May 25, 2012
Day: Friday
Time: 7:30am - 9:30am
Building(s): Bldg. 13
Room(s): MBE lab 1143, 1143A, 1150, 1155, 1157
System: AHU6 & Fan Exhaust EF15, EF16, EF17, EF18
Duration: 2 hours
Reason:
Collect mechanical drive information for future overhaul of exhaust fans.
Effect:
Loss of supply air and exhaust.