[158948] in Hotline Meeting
*2nd Extension - Bldg. 18 - All, Fire Alarm - *Live Audible Testing
daemon@ATHENA.MIT.EDU (Janine Findlay)
Thu May 24 08:41:00 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"rjwilk@mit.edu" <rjwilk@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
Ops RM Fire Protection Team <rm-fire-prot-team@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>
CC: "wradochi@mit.edu" <wradochi@mit.edu>
Date: Thu, 24 May 2012 08:40:57 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE26DBC3E@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following *extended fire alarm - *live audible testing shutdown request for Bldg. 18 - All, on Tuesday, May 22, 2012, 5:30am - 6:00am, Thursday, May 24th, 5:00am - 7:00am, *and to include Friday, May 25, 2012, 5:00am - 7:00am, is for your information and response. Any questions, please contact Bill Radochia, x3-6361.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: May 22, 24 *& 25
Day: Tuesday, Thursday, *and Friday
Time: 5:30am - 6:00am (5/22); 5am - 7am (5/24); *and 5am - 7am (5/25)
Building(s): 18
Room(s): All
System: Fire Alarm - *Live Audible Testing
Duration: 1/2 hour (5/22); 2 hours (5/24); *2 hours (5/25)
Reason:
to test horns and strobes for proper operation
*Extended request reason - to make repairs to a few problem areas discovered while testing on Tuesday. Thank you.
*2nd Extension - there are further repairs needed to assure proper operation of the horns and strobes - thank you.
Effect:
Loss of fire alarms for the duration and *live audible testing.