[158912] in Hotline Meeting
*CANCELLED - Bldg. 13 - (see list below for rooms/areas affected),
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue May 22 10:13:47 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"Ops Custodial Admin &
Support Staff" <cust-staff@mit.edu>,
"jbartels@MIT.EDU" <jbartels@mit.edu>,
"mbulsara@mit.edu" <mbulsara@mit.edu>,
"jeileef@mit.edu" <jeileef@mit.edu>, "elk@MIT.EDU" <elk@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"jingkong@mit.edu" <jingkong@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"Ops RM
Electrical Controls Team" <rm-elecctl@mit.edu>,
"rlucas@mit.edu"
<rlucas@mit.edu>, "dcrovo@mit.edu" <dcrovo@mit.edu>
CC: "biss@mit.edu" <biss@mit.edu>
Date: Tue, 22 May 2012 10:13:42 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE26DB413@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following normal building power (208V/120V) shutdown request for Bldg. 13 - (see list below for rooms/areas affected), on Friday, May 25, 2012, 12:00am - 6:00am, *has been cancelled and will be re-scheduled at a later date. Any questions, please contact Biss Teelucksingh, x2-5972.
We apologize for any confusion this may have caused.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal **CANCELLED - will be re-scheduled**
Date: May 25, 2012
Day: Friday
Time: 12:00am - 6:00am
Building(s): 13
Room(s): (see list below for rooms/areas affected
System: Normal Building Power (208V/120V)
Duration: 6 hours
Reason:
We request a bldg 13 normal 208V/120V building power shutdown from midnight to 6 AM on Friday morning, May 25th, 2012 in order to install circuit breakers and tie-in in sub panels for the 13-3rd floor NSF funded labs renovation project. We need to de-energize three of the 208V feeder risers (#'s 200, 203 and 213) in order to work in 3rd floor power panels 13C, 21C and 49. The following laboratories and offices will be affected and experience a loss of 120V and 208V power during the shutdown period; 480V power and all other building utilities will not be affected.
All room numbers 2012 to 2080
All room numbers 3011 to 3080
All room numbers 4011 to 4080
All room numbers 5016 to 5076
2148
3147
3148
3123 - 225A 208V disconnect only
4137
4139
4147
4148
5137
5147
5148
Barr and Barr Builders is the general contractor; John Bidgood 508-686-0870 Bennett Electric is the electrical subcontractor; Jim Vella 781-706-2920 MIT's project manager is Biss Teelucksingh 617-447-5081
**CANCELLED - will be re-scheduled** - we apologize but need to cancel this shutdown due to the occupant response of too much activity for the requested date. A new shutdown request will be sent with the re-scheduled dates as soon as possible. Thank you.
Effect:
Loss of normal building power (208V/120V) for the duration of the shutdown.
**CANCELLED - will be re-scheduled**