[158222] in Hotline Meeting
Re: Bldg. N51/N52 Fire Alarm Testing w/live audible 3rd party testing for sprinkler shutdown request
daemon@ATHENA.MIT.EDU (Don Stidsen)
Mon May 7 15:17:59 2012
From: Don Stidsen <dstidsen@MIT.EDU>
To: <shutdown-response@MIT.EDU>
In-Reply-To: <200B20FF4AD84283BBEF2E4612263199@facilities.ms.mit.edu>
Message-Id: <6AC01C49-3012-470B-996D-801199A2A27E@mit.edu>
Content-Type: text/plain; charset=US-ASCII; format=flowed; delsp=yes
Content-Transfer-Encoding: 7bit
Mime-Version: 1.0 (Apple Message framework v936)
Date: Mon, 7 May 2012 15:17:55 -0400
Cc: <undisclosed_recipients@MIT.EDU>, <shutdowns@MIT.EDU>, <whomeyer@MIT.EDU>
approve
Don
On May 7, 2012, at 2:31 PM, <shutdown-response@MIT.EDU> wrote:
> The following Fire Alarm Testing with live audible 3rd party testing
> for sprinkler related fire alarm devices for N51/N52-All on
> Wednesday, May 9, 2012 is for your information and response. Any any
> questions please contact Alan Legere x3-7636.
>
> Would you please let us know whether this does or does not have your
> approval.
>
> Thank you,
> Bernadette Drinkwater
> Repair and Maintenance
> x3-0938
>
> We request a bldg N51/N52 fire alarm shutdown from 6 AM to 9 AM on
> Wednesday, May 9th, 2012 to conduct *live audible 3rd party testing
> for sprinkler related fire alarm devices* associated with the
> N51-3rd floor Edgerton Lab relocation project by Bond Brothers
> (Steve Goodwin 617-212-0438/Patrick Joyce 617-895-6741). Access to
> alarmed areas is not required, thanx, Billy H. 8-0432
>
> Type: Normal
> Date: May 9, 2012
> Day: Wednesday
> Time: 6:00am - 9:00am
> Building(s): N51/N52
> Room(s): All
> System: Fire Alarm w/live audible 3rd party sprinkler related fire
> alarm devices
> Duration: 3 hours
> Reason:
> Conduct live audible 3rd party testing for new fire alarm related
> sprinkler devices.
>
> Effect:
> Fire Alarms.