Bldg. N51/N52 Fire Alarm Testing w/live audible 3rd party testing for sprinkler shutdown request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon May 7 14:32:58 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <shutdowns@MIT.EDU>, <whomeyer@MIT.EDU>
Date: Mon, 7 May 2012 14:31:12 -0400
Message-ID: <200B20FF4AD84283BBEF2E4612263199@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fire Alarm Testing with live audible 3rd party testing for sprinkler related fire alarm devices for N51/N52-All on Wednesday, May 9, 2012 is for your information and response. Any any questions please contact Alan Legere x3-7636.

Would you please let us know whether this does or does not have your approval.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938

We request a bldg N51/N52 fire alarm shutdown from 6 AM to 9 AM on Wednesday, May 9th, 2012 to conduct *live audible 3rd party testing for sprinkler related fire alarm devices* associated with the N51-3rd floor Edgerton Lab relocation project by Bond Brothers (Steve Goodwin 617-212-0438/Patrick Joyce 617-895-6741). Access to alarmed areas is not required, thanx, Billy H. 8-0432

Type: Normal
Date: May 9, 2012
Day: Wednesday
Time: 6:00am - 9:00am
Building(s): N51/N52
Room(s): All
System: Fire Alarm w/live audible 3rd party sprinkler related fire alarm devices
Duration: 3 hours
Reason: 
Conduct live audible 3rd party testing for new fire alarm related sprinkler devices.

Effect: 
Fire Alarms.