Approved - Bldg. 13 - 3rd Floor, Heating Hot Water Shutdown

daemon@ATHENA.MIT.EDU (Bernadette Drinkwater)
Fri May 4 11:12:25 2012

From: Bernadette Drinkwater <BDrink@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
        "Ops Custodial Admin &
 Support Staff" <cust-staff@mit.edu>,
        "jbartels@MIT.EDU" <jbartels@mit.edu>,
        "mbulsara@mit.edu" <mbulsara@mit.edu>,
        "jeileef@mit.edu" <jeileef@mit.edu>, "elk@MIT.EDU" <elk@mit.edu>,
        MIT Schedules Office <schedules@mit.edu>,
        "jingkong@mit.edu" <jingkong@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>
CC: "biss@mit.edu" <biss@mit.edu>, Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>
Date: Fri, 4 May 2012 11:12:20 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE128835E@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved heating hot water shutdown for Bldg. 13 - 3rd Floor, on Tuesday, May 8, 2012, 6:00am - 10:00am, is for your information. Any questions, please contact Billy Homeyer, x8-0432.

Thank you,

Bernadette Drinkwater
Repair and Maintenance
x3-0938

Type: Normal
Date: May 8, 2012
Day: Tuesday
Time: 6:00am - 10:00am
Building(s): 13
Room(s): 3rd Floor
System: Heating Hot Water
Duration: 4 hours
Reason: 
We request a bldg 13-3rd floor heating hot water shutdown (hhw to interior FCU's and reheat coils; the CV5 PMP11 system; perimeter induction units hhw is not affected)) from 6 AM to 10 AM on Tuesday, May 8th, 2012 for J C Cannistraro Mechanical (Jim AcAleer 617-293-4542) to tie-in 3 new reheat coils being installed in 13-3064 as part of the NSF funded project for this lab space by Barr and Barr Builders (John Bidgood 508-686-0870). Biss Teelucksingh 2-5972 is the MIT project manager.

Effect: 
Loss of heating hot water and supply heating air for the duration of the shutdown.  Perimeter induction units heating hot water is not affected.
 