[157764] in Hotline Meeting
Approved Bldg. 36 - Floors 2 through 8, South Side - Air Handler 8
daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed Apr 25 11:12:03 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: OPS RM Campus Services Main <rm-mcs@mit.edu>,
"herrickd@MIT.EDU"
<herrickd@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"wayneb@mit.edu"
<wayneb@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"ldargus@mit.edu"
<ldargus@mit.edu>,
"wgibbs@rle.mit.edu" <wgibbs@rle.mit.edu>,
"amcgurl@RLE.MIT.EDU" <amcgurl@rle.mit.edu>,
"barnard@mit.edu"
<barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
Ops RM Electrical Controls Team <rm-elecctl@mit.edu>,
"jmannion@mit.edu" <jmannion@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "sgilliga@mit.edu" <sgilliga@mit.edu>,
"pdoherty@mit.edu"
<pdoherty@mit.edu>
Date: Wed, 25 Apr 2012 11:11:59 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE100EFE1@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved air handler 8 (PM #702014) shutdown for Bldg. 36 - Floors 2 through 8, South Side, on Friday, April 27, 2012, 6:00am - 8:00am, is for your information. Any questions, please contact Steve Gilligan, x3-8079.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: April 27, 2012
Day: Friday
Time: 6:00am - 8:00am
Building(s): 36
Room(s): Floors 2 through 8, South Side
System: Air Handler 8 (PM #702014)
Duration: 2 hours
Reason:
for conduit comression coupling repair inside unit
Effect:
Loss of supply ventilation air and laboratory exhaust for the duration of the shutdown.