Approved Critical - Bldg. 48 - All, Lab Process Hot Water Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Apr 24 12:15:32 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Ops RM Piping Systems Team
	<rm-pipesys@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
        "darae@mit.edu" <darae@mit.edu>, "darae@mit.edu" <darae@mit.edu>,
        "sfrankel@mit.edu" <sfrankel@mit.edu>,
        "jmlong@mit.edu" <jmlong@mit.edu>, "jmac@mit.edu" <jmac@mit.edu>,
        OPS RM Campus Services Main <rm-mcs@mit.edu>,
        "sbghosh@MIT.EDU" <sbghosh@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "wayneb@mit.edu" <wayneb@mit.edu>,
        MIT Schedules Office <schedules@mit.edu>,
        "barnard@mit.edu" <barnard@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>
CC: "mmcorrei@mit.edu" <mmcorrei@mit.edu>
Date: Tue, 24 Apr 2012 12:15:28 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE100EB3D@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved critical lab process hot water shutdown for Bldg. 48 - All, on Wednesday, April 25, 2012, 5:00am - 9:00am, is for your information.  Any questions, please contact Mike Correira, x8-9174.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Critical
Date: April 25, 2012
Day: Wednesday
Time: 5:00am - 9:00am
Building(s): 48
Room(s): All
System: Lab Process Hot Water
Duration: 4 hours
Reason: 
to install a new tube bundle - this is necessary as the system is severely corroded and there is barely any lab process hot water available

Effect: 
Loss of lab process hot water for the duration of the shutdown.