[13398] in Hotline Meeting
Past Shutdowns
daemon@ATHENA.MIT.EDU (Hasan Sharif)
Fri Feb 5 13:47:11 1993
Date: Fri, 05 Feb 93 14:56:35
From: has@MIT.EDU (Hasan Sharif)
To: shutdowns@Athena.MIT.EDU
This one is kind of late folks:
Lee Ann from Ops called in early this morning and left voicemail
about two shutdowns. Unfortunately, not one checked the mail, so I'm not
sure if any of you know about these shutdowns yet. If so then please
disregard this message. If not, then it doesn't matter because the
shutdowns are done with by now anyway.
The first shutdown took place this morning from 7am to 8am. The
domestic water in building 56 was shut off. This affected the 7th and
8th floors.
The second shutdown was originally scheduled for today from 1pm
to 3pm, but was moved up to 9am. This was for the city water, domestic
hot and cold in building 54.