Project Name: Athena User Interface Project
Project Leader: Andrew Boardman
Report Date: 10 December 2001
Project URL: http://web.mit.edu/aui/notebook/
Accomplishments Past Period:
- Finalized new round of comparative usability testing.
- Celebration planned for early January.
- The one last moderately-high-profile AUI bug has been found and fixed.
Goals for Next Period:
- Find testing subjects for above. As the primary slant is at students,
however, we have not and probably will not find subjects for the test
until IAP.
Notes:
- The project is for the most part shut down; the only activity going is
the final set of usability tests.
Team Dynamics:
- Fine.