Events Calendar Monthly Project Status - March, 2001

daemon@ATHENA.MIT.EDU (Stephen Turner)
Thu Apr 5 11:24:29 2001

Message-Id: <200104051524.LAA14370@melbourne-city-street.mit.edu>
Date: Thu, 05 Apr 2001 11:21:55 -0400
To: delivery@mit.edu
From: Stephen Turner <sturner@MIT.EDU>
Cc: events-team@mit.edu
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"

Project Name: MIT Events Calendar
Project Leader: Stephen Turner
Report Date: April 5, 2001
Submitted by: Stephen Turner
URL: http://web.mit.edu/is/delivery/eventscalendar/

This Month's Accomplishments

- Completed planning the changes to the events home page.
  Passed a mockup of the screen to the usability team.
  Feedback was positive.

- Created mockups for the redesigned "group management"
  process.

- Created draft project plan for the "1.5" enhancements. 
  The plan tentatively suggests that the enhancements will
  be complete during the summer term.

- Summary of the 1.5 enhancements:

    * Modify home page (includes increased font sizes, 
      change to traditional grid-style calendar display)
    * Increase fonts on menu bar throughout calendar.
    * Change the group management process to make things
      easier for both users and system administrators.
    * Add a "preview" feature to the event edit function.
    * Add "next day" and "previous day" navigation links to
      the "today's events" screen.
    * Create a text-only version of the manage events page 
      so that users with text browsers can use this function 
      more easily.

Next Month's Plans

- Present the planned enhancements to Kathryn Willmore, the
  project sponsor and the system administrators (aka Calendar
  Coordinators) for their approval.

Issues

- None this month.