[451] in I/T Delivery

home help back first fref pref prev next nref lref last post

Enterprise Monthly Report

daemon@ATHENA.MIT.EDU (Grant Young)
Wed Mar 7 15:52:42 2001

Message-Id: <4.3.2.7.2.20010307155534.02c35530@hesiod>
Date: Wed, 07 Mar 2001 15:56:28 -0500
To: delivery@mit.edu
From: Grant Young <gyoung@MIT.EDU>
Cc: ebs-l@mit.edu, asst@mit.edu
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed

Project Name:    Enterprise Backup System
Project Leader:  Grant Young
Report Date:     March 7, 2001
URL:             http://windsurf.mit.edu/ebs


Issues:

* Scheduling hardware upgrade time on the Production SAP systems in W91 is 
complex.  There's a great deal of deferred maintenance (firmware and 
outstanding field change orders) that needs to be accomodated with 
production downtime before we can install the NetBackup software in 
W91.  Balancing continuing reliability of the production systems and 
expeditiously getting the hardware ready is a challenge.

Accomplishments Past Period:

* Continued maintence and operation of the E40 systems.

* Developed automated notification system to monitor the readiness of the E40
   systems for backup operations.

* Proposed schedule for upgrading hardware in W91 for installation of
   NetBackup to R3-Admin.  Tentative agreement on first steps.

Goals for the Coming Period

* Begin hardware reconfiguration in W91 for the rollout.

* Determine dates for rollout of online db backups in E40.

* Develop requirements and strategy for web-based reporting of backup job
   sucess and failure.

Team Dynamics:

* Good.

----------------
Grant Young, MIT Information Systems
Administrative Servers Service Team
W91-219B -- 253-7529




home help back first fref pref prev next nref lref last post