[393] in I/T Delivery

home help back first fref pref prev next nref lref last post

ITS Update

daemon@ATHENA.MIT.EDU (Mark Damian)
Fri Dec 1 09:11:56 2000

Message-Id: <200012011411.JAA11421@melbourne-city-street.MIT.EDU>
Date: Fri, 01 Dec 2000 09:11:53 -0500
To: delivery@mit.edu
From: Mark Damian <mdamian@MIT.EDU>
Cc: ljr@mit.edu
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"

Project name: Internet Transaction Server (ITS) 
Project leader: Mark Damian 
Report date: December 1, 2000 
Submitted by: Mark Damian
url: web.mit.edu/its-alive

Accomplishments past period: 
- Was successful in installing ITS 4.6D to connect to a 4.6C application
server
- Began evaluation of ITS Pilot transactions with 4.6

Goals for the coming period
- Finish evaluation of Pilot transactions with SAP 4.6C
- Receive strategic direction from Management for ITS deployment
- Work on drafting ITS hardware and development standards support
        mechanisms

Issues
-  The SAP 4.6C upgrade has taken some ITS resources
        away from our project.
-  The SNC error is still being researched by our MIT Kerberos experts.
        With this solved, we can move from pilot to general rollout.

Team Dynamics
Things are OK.

Closing
Our sponsors have agreed that we have completed our objectives
of the original project and next month's report will be our last
submittal.  New efforts on ITS will be identified as unique projects
which may have their own delivery reports.



Sincerely,

Mark Damian
MIT Financial Systems Services
Sr. Business Systems Analyst
(617)258-0737
fax (617)253-9661

home help back first fref pref prev next nref lref last post