Project name: Internet Transaction Server (ITS)
Project leader: Mark Damian
Report date: December 1, 2000
Submitted by: Mark Damian
url: web.mit.edu/its-alive
Accomplishments past period:
- Was successful in installing ITS 4.6D to connect to a 4.6C application
server
- Began evaluation of ITS Pilot transactions with 4.6
Goals for the coming period
- Finish evaluation of Pilot transactions with SAP 4.6C
- Receive strategic direction from Management for ITS deployment
- Work on drafting ITS hardware and development standards support
mechanisms
Issues
- The SAP 4.6C upgrade has taken some ITS resources
away from our project.
- The SNC error is still being researched by our MIT Kerberos experts.
With this solved, we can move from pilot to general rollout.
Team Dynamics
Things are OK.
Closing
Our sponsors have agreed that we have completed our objectives
of the original project and next month's report will be our last
submittal. New efforts on ITS will be identified as unique projects
which may have their own delivery reports.
Sincerely,
Mark Damian
MIT Financial Systems Services