Project Name:   Enterprise Backup Service Delivery
Project Leader: Rachel Sage
Report Date:    June 28, 2000
Submitted by:   Rachel Sage
URL:            http://windsurf.mit.edu/ebs/

Accomplishments Past Period:

* Launched project team
* Created project notebook/web site
* Negotiated consulting services with Veritas
* Completed pre-installation checklist for Veritas
* Completed site prep for new hardware, including power, new
  network ports and console management in W91 and E40.


Goals for the Coming Period

* Receive and install all hardware for project
* Install/configure operating systems on new backup servers
* NetBackup training for new employee
* Define NetBackup configurations
* Install NetBackup in E40 and W91
* Develop test plan
* Complete initial configuration and testing
* Start SAP/Oracle online backup testing


Issues:

* Unknown hardware arrival dates have us scrambling to make sure that
  we have all hardware installed before the Veritas consultant arrives
  to help with software configuration.


Additional Comments: