[2875] in SIPB-AFS-requests

home help back first fref pref prev next nref lref last post

Server hardware for FY98

daemon@ATHENA.MIT.EDU (Jonathon Weiss)
Mon Oct 27 18:41:39 1997

From: Jonathon Weiss <jweiss@MIT.EDU>
To: star-maintainers@MIT.EDU
Date: Mon, 27 Oct 1997 18:41:24 EST


I'm going ot need to supply a proposed budget for server hardware RSN
(order of a couple of weeks) This means I need to have some idea of
what SIPB needs RFSN (by the end of the week would be nice).  It
doesn't have to be exact, just some idea of what and how much.  For
instance, charon-maintainers could say they needed a new machine that
would probably be a PC and cost about $5k.  (Assuming that's accurate,
which I think it is except possibly for the cost.)  As was the case
last year, an list of wants that are seperate from the needs would be
useful.  As of right now Teh only thing I know people want to buy is a
replacement for charon.  I have a hard time believing that none of the
other services will need hardware before 7/1/98.

	Jonathon