[6700] in APO Printshop
Re: FW: W20 access to rooms 450 and 454
daemon@ATHENA.MIT.EDU (Leonard H Tower Jr.)
Fri Jul 12 19:36:20 2013
Date: Fri, 12 Jul 2013 19:36:06 -0400 (EDT)
From: "Leonard H Tower Jr." <tower@alum.mit.edu>
To: Benjamin Kaduk <kaduk@mit.edu>
cc: "apo-exec@mit.edu" <apo-exec@mit.edu>, lsc@mit.edu, apo-printshop@mit.edu,
apo-silkscreen@mit.edu
In-Reply-To: <alpine.GSO.1.10.1307121903420.26275@multics.mit.edu>
(Ben: You had "July 20th" below, but I'm sure you meant "July 13th".)
Only one day notice???? (from CAC???).
[Sigh ** Sigh]
I can't come down tonight.
Two plus hours commute,
and an exhausitng 30 minutes to move the cabinet by myself.
With more notice, the type cabinet on the large cart could have moved
to W20-415 for a few days.
LSC might have moved the photo processor to their press room.
It's on a cart.
thanks.
yiLFS -len
Date: Fri, 12 Jul 2013 19:07:51 -0400 (EDT)
From: Benjamin Kaduk <kaduk@MIT.EDU>
To: Leonard H Tower Jr. <tower@alum.MIT.EDU>
Cc: "apo-exec@mit.edu" <apo-exec@mit.edu>, lsc@mit.edu,
apo-printshop@mit.edu, apo-silkscreen@mit.edu
Subject: Re: FW: W20 access to rooms 450 and 454
Hi Len,
On Fri, 12 Jul 2013, Leonard H Tower Jr. wrote:
> Ben:
>
> They should NOT move the lead type cabinet.
They are not planning to move the lead type cabinet.
They saw the "fragile" signs and want to respect them.
They can work around the cabinet where it is, but could benefit from the
extra space if it was easy to move.
> It's missing four internal tie rods.
> (Press Shopers:
> If anyone want to get buy tie rods and install them,
> get in touch with me separately.)
>
> And even if had them, you have to remove all the trays,
> then move the cabinet, then put the trays back.
>
> They could move and return the stuff on top.
>
> When are they starting this work?
> When will they be done?
Per Claudette's email to w20-occupants,
"Please be advised that Elaine Construction will be working in W20 from 6 am
- 2 pm tomorrow, Saturday, July 13th."
The email that only apo-exec saw (apparently I trimmed context) has:
They would like to have access these rooms starting at 6am to 2pm this
Saturday, July 20th to do some exploration and run the pipe through the
spaces above the ceilings. They hope to be finished in one day, however, may
need to get into these rooms again on Monday, July 15th from 6am to 2pm.
-Ben Kaduk