Re: Bldg. 9 - Revised Air Handler 1 Shutdown Request
daemon@ATHENA.MIT.EDU (Meg Westlund)
Fri Jan 30 10:49:17 2004
Message-Id: <5.2.1.1.2.20040130104448.00b8f310@hesiod>
Date: Fri, 30 Jan 2004 10:45:13 -0500
To: Andrea Nichols <andrea@plant.mit.edu>, C-Zone <C-Zone@MIT.EDU>,
Cust-Coach <cust-coach@MIT.EDU>, "'gallant@mit.edu'" <gallant@MIT.EDU>,
"'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'jsoroko@mit.edu'" <jsoroko@MIT.EDU>,
"'kirky@ceci.mit.edu'" <kirky@ceci.mit.edu>,
"'kmartel@mit.edu'" <kmartel@MIT.EDU>,
"'mcurtin@mit.edu'" <mcurtin@MIT.EDU>,
"'mlavalle@mitvma.mit.edu'" <mlavalle@mitvma.mit.edu>,
"'ndk@mit.edu'" <ndk@MIT.EDU>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
"'randy@mit.edu'" <randy@MIT.EDU>, "'src@mit.edu'" <src@MIT.EDU>,
"'westlund@mit.edu'" <westlund@MIT.EDU>,
"'wjfitz@mit.edu'" <wjfitz@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
From: Meg Westlund <westlund@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
In-Reply-To: <568F0AEE7A57D511923900508B55645103D72060@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed
Thanks, Andrea, I think we can live with that.
meg
At 10:14 AM 1/30/2004 -0500, Andrea Nichols wrote:
>To: C-Zone; Cust-Coach; gallant@mit.edu; jobrien@mit.edu;
>jsoroko@mit.edu; kirky@ceci.mit.edu; kmartel@mit.edu; mcurtin@mit.edu;
>mlavalle@mitvma.mit.edu; ndk@mit.edu; pam@ceci.mit.edu; randy@mit.edu;
>src@mit.edu; westlund@mit.edu; wjfitz@mit.edu; shutdowns@mit.edu
>
>Cc: shutdown@plant.mit.edu
>Subject: Bldg. 9 - Revised Air Handler 1 Shutdown Request
>
>The following revised air handler 1 shutdown request for Bldg. 9 - floors
>2 through 5 on Wednesday, 2/4/04 is again for your information and
>comment. Would you please let me know whether this does or does not meet
>with your approval.
>
>Thank you again for your time.
>
>Andrea Nichols
>Repair and Maintenance
>8-7872
>
>Status: Normal
>Building: 9 - floors 2 through 5
>Date: 2/4/2004
>Day: Wednesday
>Time: 6 AM - 8 AM
>System: Air Handler 1
>Duration: 2 hours
>Reason:
>Preventive maintenance work on fan.
>
>Effect:
>Loss of supply ventilation, supply cooling and supply heating in the
>above-listed areas during the 2-hour preventive maintenance shutdown work.
Meg (Mary E.) Westlund
Administrative and Facilities Coordinator
Center for Educational Computing Initiatives (CECI)
Massachusetts Institute of Technology
Rm. 9-315, 77 Massachusetts Avenue
Cambridge, MA 02139
Tel. (617) 253-7663
Fax.(617) 253-8632
email: westlund@mit.edu
http://www-caes.mit.edu