[70385] in Hotline Meeting
Bldg. 44 - All Steam/Condensate Return Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Dec 8 13:44:27 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71E1A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, "'fisherp@mit.edu'" <fisherp@MIT.Edu>,
"'khewitt@mit.edu'" <khewitt@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 8 Dec 2003 13:38:49 -0500
> To: D-Zone; fisherp@mit.edu; khewitt@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 44 - All Steam/Condensate Return Shutdown Request
>
>
The following all steam/condensate return shutdown request for Bldg. 44 on
Thursday, 12/11/03 is for your information and comment. Would you please
let me know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 44
> Date: 12/11/2003
> Day: Thursday
> Time: 9 AM - 5 PM
> System: All Steam Condensate Return
> Duration: 8 hours
> Reason:
> To repair steam leak.
>
> Effect:
> Loss of all steam and condensate in Bldg. 44 means there will be no hot
> domestic water (affects bathroom and kitchen sink faucets), no hot lab
> process water (affects lab sink faucets), or heating hot water (building
> steam heat) during the shutdown period.
>
>