[70383] in Hotline Meeting
Bldg. 38 - Low Pressure Steam Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Dec 8 13:12:50 2003
Message-ID: <568F0AEE7A57D511923900508B55645103D71E18@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'agallant@mit.edu'" <agallant@mit.edu>,
"'amcgurl@rle.mit.edu'"
<amcgurl@rle.mit.edu>,
B-Zone <B-Zone@mit.edu>, Cust-Coach
<cust-coach@mit.edu>,
"'edc@mit.edu'" <edc@mit.edu>, "'pmorley@mit.edu'"
<pmorley@mit.edu>,
"'rroscoe@mit.edu'" <rroscoe@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'wrgibbs@rle.mit.edu'"
<wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 8 Dec 2003 13:12:43 -0500
> To: agallant@mit.edu; amcgurl@rle.mit.edu; B-Zone; Cust-Coach;
> edc@mit.edu; pmorley@mit.edu; rroscoe@mit.edu; schedule@mit.edu;
> wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 38 - Low Pressure Steam Shutdown Request
>
>
The following low pressure steam shutdown request for Bldg. 38 on Wednesday,
12/10/03 is for your information and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 38
> Date: 12/10/2003
> Day: Wednesday
> Time: 6 AM - 10 AM
> System: Low Pressure steam
> Duration: 4 hours
> Reason:
> Tie-in service to new air handling unit.
>
> Effect:
> Loss of low pressure steam in Bldg. 38. This means there will be no
> heating hot water (steam heat) for the building or supply heating via
> ceiling supply fans during the 4-hour shutdown period.
>
>