Bldg. E34 - Revised Hot and Cold Domestic/Lab Process Water Shutd
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 3 11:15:51 2002
Message-ID: <568F0AEE7A57D511923900508B556451012321BE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, "'jsachs@mit.edu'" <jsachs@MIT.Edu>,
"'politano@mit.edu'" <politano@MIT.Edu>,
"'wendell@mit.edu'"
<wendell@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 3 Jul 2002 11:15:40 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: E-Zone; jsachs@mit.edu; politano@mit.edu; wendell@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E34 - Revised Hot and Cold Domestic/Lab Process Water
> Shutdown Request
>
>
The following revised Hot and Cold Domestic/Lab Process Water shutdown
request for Bldg. 34 now on Thursday, July 11 and Friday, July 12 is again
for your review and comment. Would you please let me know whether this does
or does not meet with your approval.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E34
> Date: 7/11/2002
> Day: Thursday
> Time: 6 AM - 9 AM for 2 days
> System: Hot/Cold Domestic/Lab Process Water
> Duration: 2 days @ 3 hours each day
> Reason:
> Tie-in new water services to new fifth floor lab.
>
> Effect:
> Loss of hot and cold domestic water (affects toilets, bathroom, kitchen,
> lab sink faucets and drinking fountains) and hot and cold lab process
> water. This affects lab equipment requiring use of same to be operational
> during the 2-day/3-hour per day shutdown period.
>
>