Bldg. 54 - Steam Station Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jul 1 13:58:48 2002

Message-ID: <568F0AEE7A57D511923900508B5564510123218C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'graposa@MIT.EDU'" <graposa@MIT.Edu>,
        "'kvkeefe@mit.edu'"
	 <kvkeefe@MIT.Edu>,
        "'politano@mit.edu'" <politano@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'"
	 <sdl-adm-lib@MIT.Edu>,
        "'w1mx-officers@mit.edu'" <w1mx-officers@MIT.Edu>,
        "'wendell@mit.edu'" <wendell@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 1 Jul 2002 13:58:30 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; Cust-Coach; graposa@MIT.EDU; kvkeefe@mit.edu;
> politano@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> w1mx-officers@mit.edu; wendell@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 54 - Steam Station Shutdown Request
> 
> 
The following steam station shutdown request for Bldg. 54 on Tuesday, July 9
is for your information and comment.  Would you please let me know whether
this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 54
> Date: 7/9/2002
> Day: Tuesday
> Time: 9 AM - 1:30 PM
> System: Steam Station
> Duration: 4 1/2 hours
> Reason: 
> To repair flange on strainer.
> 
> Effect: 
> Loss of high, medium and low pressure steam.  This means that no hot
> domestic water (for bathroom, kitchen and lab sink faucets), hot lab
> process water (for lab equipment, and heating hot water (building heat)
> will not be operational during the shutdown period.
> 
> 