Re: Bldg. 9 - Chilled Water/Supply Cooling Shutdown Request

daemon@ATHENA.MIT.EDU (Meg Westlund)
Thu May 2 14:38:00 2002

Message-Id: <5.0.2.1.2.20020502143622.00aceb88@hesiod>
Date: Thu, 02 May 2002 14:36:53 -0400
To: Andrea Nichols <andrea@PLANT.MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
        Cust-Coach <cust-coach@MIT.EDU>, "'deedc@mit.edu'" <deedc@MIT.EDU>,
        "'gallant@mit.edu'" <gallant@MIT.EDU>,
        "'jobrien@mit.edu'" <jobrien@MIT.EDU>,
        "'kirky@ceci.mit.edu'" <kirky@ceci.mit.edu>,
        "'mcurtin@mit.edu'" <mcurtin@MIT.EDU>,
        "'mlavalle@mitvma.mit.edu'" <mlavalle@MITVMA.MIT.EDU>,
        "'ndk@mit.edu'" <ndk@MIT.EDU>, "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
        "'randy@mit.edu'" <randy@MIT.EDU>,
        "'smathis@mit.edu'" <smathis@MIT.EDU>, "'src@mit.edu'" <src@MIT.EDU>,
        "'wjfitz@mit.edu'" <wjfitz@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'lordjim@mit.edu'" <lordjim@MIT.EDU>
From: Meg Westlund <westlund@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
In-Reply-To: <568F0AEE7A57D511923900508B55645101231DF6@PLANT.MIT.EDU>
Mime-Version: 1.0
Content-Type: text/plain; charset="us-ascii"; format=flowed

You have the "go-ahead",  Andrea. Thanks,
meg


At 02:18 PM 5/2/2002 -0400, Andrea Nichols wrote:
> > To:   C-Zone; Cust-Coach; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> > kirky@ceci.mit.edu; mcurtin@mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu;
> > pam@ceci.mit.edu; randy@mit.edu; smathis@mit.edu; src@mit.edu;
> > westlund@mit.edu; wjfitz@mit.edu; shutdowns@mit.edu; lordjim@mit.edu
> > Cc:   shutdown@plant.mit.edu
> > Subject:      Bldg. 9 - Chilled Water/Supply Cooling Shutdown Request
> >
> >
>The following chilled water/supply cooling shutdown for Bldg. 9 - all rooms
>with fan coil units in the basement and floors 2 through 6 on Thursday, 5/9
>is for your information and comment.  Would you please let me know whether
>this does or does not meet with your approval.
>
>Thank you.
>
>Andrea Nichols
>Repair and Maintenance
>8-7872
>
> > Status: Normal
> > Building: 9 - all rooms with fan coil units in the basement and floors 2
> > through 6
> > Date: 5/9/2002
> > Day: Thursday
> > Time: 6 AM - 9 AM
> > System: Chilled Water/Supply Cooling
> > Duration: 3 hours
> > Reason:
> > Tie in chilled water to new fan coil unit in 9-220.
> >
> > Effect:
> > Loss of chilled water (air conditioning) and supply cooling (via ceiling
> > supply fans) in the above listed areas only during the shutdown period.
> >
> >