Bldg. 9 - Chilled Water/Supply Cooling Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 2 14:18:26 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231DF6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'deedc@mit.edu'" <deedc@MIT.Edu>,
        "'gallant@mit.edu'" <gallant@MIT.Edu>,
        "'jobrien@mit.edu'" <jobrien@MIT.Edu>,
        "'kirky@ceci.mit.edu'"
	 <kirky@ceci.mit.edu>,
        "'mcurtin@mit.edu'" <mcurtin@MIT.Edu>,
        "'mlavalle@mitvma.mit.edu'" <mlavalle@mitvma.mit.edu>,
        "'ndk@mit.edu'"
	 <ndk@MIT.Edu>,
        "'pam@ceci.mit.edu'" <pam@ceci.mit.edu>,
        "'randy@mit.edu'" <randy@MIT.Edu>,
        "'smathis@mit.edu'" <smathis@MIT.Edu>, "'src@mit.edu'" <src@MIT.Edu>,
        "'westlund@mit.edu'" <westlund@MIT.Edu>,
        "'wjfitz@mit.edu'" <wjfitz@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>,
        "'lordjim@mit.edu'" <lordjim@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 2 May 2002 14:18:23 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	C-Zone; Cust-Coach; deedc@mit.edu; gallant@mit.edu; jobrien@mit.edu;
> kirky@ceci.mit.edu; mcurtin@mit.edu; mlavalle@mitvma.mit.edu; ndk@mit.edu;
> pam@ceci.mit.edu; randy@mit.edu; smathis@mit.edu; src@mit.edu;
> westlund@mit.edu; wjfitz@mit.edu; shutdowns@mit.edu; lordjim@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 9 - Chilled Water/Supply Cooling Shutdown Request
> 
> 
The following chilled water/supply cooling shutdown for Bldg. 9 - all rooms
with fan coil units in the basement and floors 2 through 6 on Thursday, 5/9
is for your information and comment.  Would you please let me know whether
this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 9 - all rooms with fan coil units in the basement and floors 2
> through 6
> Date: 5/9/2002
> Day: Thursday
> Time: 6 AM - 9 AM
> System: Chilled Water/Supply Cooling
> Duration: 3 hours
> Reason: 
> Tie in chilled water to new fan coil unit in 9-220.
> 
> Effect: 
> Loss of chilled water (air conditioning) and supply cooling (via ceiling
> supply fans) in the above listed areas only during the shutdown period.
> 
> 