Bldg. 45 - Chilled Water/Supply Cooling Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Apr 19 10:18:56 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231DAD@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Chris Downey <downey@PLANT.MIT.EDU>, D-Zone <D-Zone@mit.edu>,
        "'scrowley@mit.edu'" <scrowley@mit.edu>,
        "'tweidner@MIT.EDU'"
	 <tweidner@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 19 Apr 2002 10:18:54 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	Chris Downey; D-Zone; scrowley@mit.edu; tweidner@MIT.EDU;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 45 - Chilled Water/Supply Cooling Shutdown Request
> 
> 
The following chilled water/supply cooling shutdown request for Bldg. 45 on
Tuesday, 4/23 AM through Wednesday,4/23 PM is again for your review and
comment.  Would you please let me know whether this does or does not meet
with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872 

> Status: Normal
> Building: 45
> Date: 4/23/2002
> Day: Tuesday
> Time: 7 AM (4/23) - 5 PM (4/24)
> System: Chilled Water/Supply Cooling
> Duration: 34 hours
> Reason: 
> Relocate piping at rear of building 45 parking lot.
> 
> Effect: 
> Loss of chilled water (air conditioning) and supply cooling (via ceiling
> fans) in Bldg. 45 during the 34 hour shutdown period.
> 
> 