Bldg. 66 - Air Handler 1 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Apr 19 09:11:39 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231DA8@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'kkgleasn@mit.edu'" <kkgleasn@MIT.Edu>,
"'patsys@mit.edu'"
<patsys@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'swetzel@mit.edu'" <swetzel@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 19 Apr 2002 09:11:36 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; kkgleasn@mit.edu; patsys@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 - Air Handler 1 Shutdown Request
>
>
The following Air Handler 1 shutdown request for Bldg. 66 - Floors 1 thru 5
North on Thursday, 4/25, Friday, 4/26 and Saturday, 4/27 is for your review
and comment. Would you please let me know whether this does or does not
meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - floors 1 thru 5 North
> Date: 4/25/2002
> Day: Thursday
> Time: 7 AM - 3 PM each day
> System: Air Handler 1
> Duration: 8 hours each day for 3 days
> Reason:
> Remove coils (cooling). To be replaced at a future date.
>
> Effect:
> Loss of chilled water, supply ventilation and supply cooling in the
> above-listed areas.
>
>