Bldg. 54 - Air Handler 1 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Mar 8 10:15:03 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231B09@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'graposa@MIT.EDU'" <graposa@MIT.Edu>,
        "'kvkeefe@mit.edu'"
	 <kvkeefe@MIT.Edu>,
        "'politano@mit.edu'" <politano@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'"
	 <sdl-adm-lib@MIT.Edu>,
        "'w1mx-officers@mit.edu'" <w1mx-officers@MIT.Edu>,
        "'wendell@mit.edu'" <wendell@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 8 Mar 2002 10:14:55 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; Cust-Coach; graposa@MIT.EDU; kvkeefe@mit.edu;
> politano@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> w1mx-officers@mit.edu; wendell@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 54 - Air Handler 1 Shutdown Request
> 
> 
The following air handler 1 shutdown request for Bldg. 54 - North Side on
Wednesday, 3/20 is for your information.  Would you please let me know
whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 54 - North Side
> Date: 3/20/2002
> Day: Wednesday
> Time: 8 AM - 12 Noon
> System: Air Handler 1/Supply Air
> Duration: 4 hours
> Reason: 
> Trouble shoot variable speed drive.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating in Bldg. 54
> - north side only during the 4-hour shutdown period.
> 
> 