[58547] in Hotline Meeting
Bldg. 6 - Rescheduled Water/Drainage Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 6 10:48:01 2002
Message-ID: <568F0AEE7A57D511923900508B556451156573@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'chemistryhq@mit.edu'" <chemistryhq@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>, "'gsj@mit.edu'" <gsj@MIT.Edu>,
"'jsheytan@mit.edu'" <jsheytan@MIT.Edu>,
"'khewitt@mit.edu'"
<khewitt@MIT.Edu>,
"'mhankin@mit.edu'" <mhankin@MIT.Edu>,
"'rhasselt@MIT.EDU'" <rhasselt@MIT.Edu>,
"'rjwilk@mit.edu'"
<rjwilk@MIT.Edu>,
"'rrdasari@mit.edu'" <rrdasari@MIT.Edu>,
"'saraf@mit.edu'" <saraf@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'serotek@mit.edu'" <serotek@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'heatherg@mit.edu'"
<heatherg@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 6 Mar 2002 10:47:51 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; chemistryhq@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; gsj@mit.edu; jsheytan@mit.edu; khewitt@mit.edu;
> mhankin@mit.edu; rhasselt@MIT.EDU; rjwilk@mit.edu; rrdasari@mit.edu;
> saraf@mit.edu; schedule@mit.edu; serotek@mit.edu; shutdowns@mit.edu;
> heatherg@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 6 - Rescheduled Water/Drainage Shutdown Request
>
>
>
The following rescheduled pure, hot and cold domestic and lab process water
as well as lab waste and sanitary drainage shutdown request for Bldg. 6 now
on Friday, 3/15 PM to Saturday, 3/16 AM is again for your information and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 6 - entire building
> Date: 3/15/2002
> Day: Friday
> Time: 7 PM (3/15) - 7 AM (3/16)
> System: Pure, Hot and Cold Domestic, Hot and Cold Lab Process water; Lab
> Waste and Sanitary Drainage;
> Duration: 12 hours
> Reason:
> Temporarily divert lab waste water from Building 6 to 18 into holding
> tank.
>
> Effect:
> Loss of pure water, hot and cold domestic water, hot and cold lab waste
> water and lab waste and sanitary drainage. This means that no bathroom,
> kitchen and lab sink faucets, emergency showers, equipment requiring the
> use of hot and cold lab process water to operate or lab waste and sanitary
> drainage will be operational during the 12-hour shutdown period.
>
>