[58497] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 8 - Pre-test - Live Audible Testing/Fire Alarm System

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 28 12:25:13 2002

Message-ID: <568F0AEE7A57D511923900508B556451156518@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'carolr@mit.edu'" <carolr@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
        "'glabonte@mit.edu'" <glabonte@MIT.Edu>,
        "'kmartel@mit.edu'"
	 <kmartel@MIT.Edu>,
        "'lechtman@mit.edu'" <lechtman@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 28 Feb 2002 12:25:09 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	C-Zone; carolr@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; kmartel@mit.edu; lechtman@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 8 - Pre-test - Live Audible Testing/Fire Alarm System
> 
> 
The following pre-test - live audible testing of the fire alarm system for
Bldg. 8 on Wednesday, 3/6 is for your review and comment.  Would you please
let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 8 - entire building
> Date: 3/6/2002
> Day: Wednesday
> Time: 7 AM - 11 AM
> System: Fire Alarm/*live audible testing of the fire alarm from 10:30 AM -
> 11:00 AM
> Duration: 4 hours
> Reason: 
> Tie-in two new smokes and 1 horn/strobe; pre-test Rm. 8-410.
> 
> Effect: 
> There will be live audible testing of the fire alarm system from 10:30 AM
> to 11 AM.  If there is an emergency in the building during the 4-hour
> shutdown period, please dial either X100 or FIXIT (3-4948) to report it.
> Thank you.
> 
> 

home help back first fref pref prev next nref lref last post