Bldg. 6 - Water/Drainage Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 27 11:21:38 2002

Message-ID: <568F0AEE7A57D511923900508B5564511564FA@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'efrank@mit.edu'" <efrank@mit.edu>,
        "'chemistryhq@mit.edu'"
	 <chemistryhq@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>, "'ghughes@mit.edu'" <ghughes@mit.edu>,
        "'glabonte@mit.edu'"
	 <glabonte@mit.edu>,
        "'gsj@mit.edu'" <gsj@mit.edu>,
        "'jsheytan@mit.edu'"
	 <jsheytan@mit.edu>,
        "'khewitt@mit.edu'" <khewitt@mit.edu>,
        "'mhankin@mit.edu'" <mhankin@mit.edu>,
        "'rhasselt@MIT.EDU'"
	 <rhasselt@mit.edu>,
        "'rjwilk@mit.edu'" <rjwilk@mit.edu>,
        "'rrdasari@mit.edu'" <rrdasari@mit.edu>,
        "'saraf@mit.edu'"
	 <saraf@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'serotek@mit.edu'" <serotek@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>,
        "'heatherg@mit.edu'" <heatherg@mit.edu>,
        "'rjwilk@mit.edu'" <rjwilk@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        C-Zone
	 <C-Zone@mit.edu>
Date: Wed, 27 Feb 2002 11:21:25 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	efrank@mit.edu; chemistryhq@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; gsj@mit.edu; jsheytan@mit.edu; khewitt@mit.edu;
> mhankin@mit.edu; rhasselt@MIT.EDU; rjwilk@mit.edu; rrdasari@mit.edu;
> saraf@mit.edu; schedule@mit.edu; serotek@mit.edu; shutdowns@mit.edu;
> heatherg@mit.edu; rjwilk@mit.edu
> Cc: 	shutdown@plant.mit.edu; C-Zone
> Subject: 	Bldg. 6 - Water/Drainage Shutdown Request
> 
> 
The following pure, hot and cold domestic and lab process water as well as
lab waste and sanitary drainage shutdown request for Bldg. 6 on Friday, 3/8
PM to Saturday, 3/9 AM is for your information and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 6 - entire building
> Date: 3/8/2002
> Day: Friday
> Time: 7 PM (3/8) - 7 AM (3/9)
> System: Pure, Hot and Cold Domestic, Hot and Cold Lab Process water; Lab
> Waste and Sanitary Drainage;
> Duration: 12 hours
> Reason: 
> Temporarily divert lab waste water from Building 6 to 18 into holding
> tank.
> 
> Effect: 
> Loss of pure water, hot and cold domestic water, hot and cold lab waste
> water and lab waste and sanitary drainage.  This means that no toilets,
> bathroom, kitchen and lab sink faucets, emergency showers, equipment
> requiring the use of hot and cold lab process water to operate or lab
> waste and sanitary drainage will be operational during the 12-hour
> shutdown period.
> 
> 