[53415] in Hotline Meeting
Shutdown request for building 26 on 1/16
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Jan 12 13:33:38 2001
Message-Id: <82F0D564C5ADD31180EF00508B556451D2C270@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: almcgurl@MIT.EDU, andreab@MIT.EDU, B-Zone <B-Zone@MIT.EDU>,
Cust-Coach
<cust-coach@MIT.EDU>, dudley@MIT.EDU, gfp170@rle.mit.edu,
kates@MIT.EDU, ljtrudel@MIT.EDU, lsc@MIT.EDU, mhankin@MIT.EDU,
nsteele@MIT.EDU, radams@MIT.EDU, safety@MIT.EDU, schedule@MIT.EDU,
shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 12 Jan 2001 13:33:00 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: almcgurl@mit.edu; andreab@mit.edu; B-Zone; Cust-Coach;
> dudley@mit.edu; gfp170@rle.mit.edu; kates@mit.edu; ljtrudel@mit.edu;
> lsc@mit.edu; mhankin@mit.edu; nsteele@mit.edu; radams@mit.edu;
> safety@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 26 on 1/16
>
>
The following shutdown request is for building 26 4th floor on 1/16. Please
let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 26 fourth floor
> Date: 1/16/01
> Day: Tuesday
> Time: 7:30 AM - 3:30 PM
> System: Chilled water
> Duration: 8 hours
> Reason:
> Tie in new chilled water lines.
>
>
>
> Effect:
> There will be a loss of chilled water during this time.
>
>