RE: Case 196404: This case has recently been updated

daemon@ATHENA.MIT.EDU (Gerry Hughes)
Fri Jan 5 10:27:29 2001

Message-Id: <82F0D564C5ADD31180EF00508B5564511BD4D0@PLANT.MIT.EDU>
From: Gerry Hughes <ghughes@PLANT.MIT.EDU>
To: "'hotline@MIT.EDU'" <hotline@MIT.EDU>,
        Gerry Hughes
	 <ghughes@PLANT.MIT.EDU>
Cc: A-Zone <A-Zone@MIT.EDU>
Date: Fri, 5 Jan 2001 10:27:25 -0500 
Mime-Version: 1.0
Content-Type: text/plain

10-4 Tuesday 1/9/01  We can plan to go in 66-080 Athena Cluster then.

Thanks

Gerald Hughes
M.I.T.   Facilities
617-253-7636


-----Original Message-----
From: hotline@MIT.EDU [mailto:hotline@MIT.EDU]
Sent: Friday, January 05, 2001 8:28 AM
To: GHUGHES@plant.mit.edu
Cc: a-zone@MIT.EDU
Subject: Case 196404: This case has recently been updated


Case 196404 has recently been updated and stands as follows.
Please retain the case number in the subject line for future replies
connected with this case.

Most recent entry
=================
(Comment [01/05/2001 08:28:10 by jjmorey])

gerry-

lets shoot for tues 9th, i'll close the cluster from 7:30am-
1pm that should give you enough time?

john morey
hardware services team leader

Case History
============

Email Received [01/05/2001 06:11:04 by daemon]

Date: Fri, 5 Jan 2001 06:10:59 -0500 
To: hotline@MIT.EDU
From: Gerry Hughes <ghughes@PLANT.MIT.EDU>
Cc: A-Zone <A-Zone@MIT.EDU>
Subject: RE: 66-080  request to enter and perform maint.

Hi again,
 
    At this time I would ask to accept re-submittal for room shutdown for
purposes of fan coil check out and maintenance and ceiling tiles restored
and or replaced and any others needs which may be good to have done at this
time. Please let us know and give us a day in which to attempt these needs.?
 
Thank You
 
Gerald Hughes
M.I.T.   Facilities
617-253-7636

-----Original Message-----
From: Gerry Hughes [mailto:ghughes@PLANT.MIT.EDU]
Sent: Monday, December 11, 2000 1:29 PM
To: hotline@MIT.EDU
Cc: A-Zone
Subject: 66-080 request to enter and perform maint.


HI,
 
   There are some ceiling tiles which are in need of repair and or
replacement and we would also like to check the fan coil units also. Please
let us know when a good time would be. We would need a couple to a few
hours on our end. Send reply to a-zone@mit.edu <mailto:a-zone@mit.edu>
Please. We were thinking next week or thereafter when the winter break is in
session.
 
Thanks
 
Gerald Hughes
M.I.T.   Facilities
617-253-7636
 



** Attachment decoded: part2 (text/html) 2841 bytes
** <https://casetracker.mit.edu/fcgi-bin/ctfile?id=3489&case_id=196404>


Assigned Case [01/05/2001 08:28:09 by jjmorey]

Case assigned to consultant jjmorey.

home help back first fref pref prev next nref lref last post