Bldgs. 37and 31 (480V) 6/29-30 - Approved Normal Electrical Power

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 28 09:46:41 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451104F92@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
        "'cperry@mit.edu'"
	 <cperry@MIT.EDU>,
        "'pbaratta@mit.edu'" <pbaratta@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>,
        "'wpwohlfa@mit.edu'"
	 <wpwohlfa@MIT.EDU>,
        Paul Stordy <PStordy@PLANT.MIT.EDU>,
        "'mmoreira@plant.mit.edu'" <mmoreira@plant.mit.edu>,
        B-Zone
	 <B-Zone@MIT.EDU>
Cc: RM-2ndShift <rm-2ndshift@MIT.EDU>, RM-3rdShift <rm-3rdshift@MIT.EDU>,
        RM-ElecCtl <rm-elecctl@MIT.EDU>, RM-Utl <rm-utl@MIT.EDU>,
        "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>
Date: Wed, 28 Jun 2000 09:46:20 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	dcarlson@mit.edu; cperry@mit.edu; pbaratta@mit.edu;
> mmahoney@mit.edu; wpwohlfa@mit.edu; Paul Stordy; mmoreira@plant.mit.edu;
> B-Zone
> Cc: 	RM-2ndShift; RM-3rdShift; RM-ElecCtl; RM-Utl;
> shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu
> Subject: 	Bldgs. 37and 31 (480V) 6/29-30 - Approved Normal Electrical
> Power Shutdown Request - Phase 2 
> 
> 
The following approved Normal Electrical Power shutdown for Bldg. 37 and 31
(480V) on Thursday, PM - Friday, June 30 AM is for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building:  37and 31 
> Date: 6/29/30
> Day: Thursday
> Time: 7 PM (6/29) - 3 AM (6/30)
> System: Normal electrical power and 480V in Bldg. 31
> Duration: 8 hours
> Reason: 
> Second shutdown request out of three to replace high voltage substation
> switches.
> 
> Effect: 
> Loss of normal electrical power in Bldg. 37 (i.e., access controls,
> building power (supply ventilation), elevators, computers, lighting in
> corridors and stairs (with the exception of athena rooms). Loss of 480V
> power in Bldg. 31 (equipment or machinery) operated by 480V.
> 
> 