[51231] in Hotline Meeting
Bldg. 1 - 151, 153, 163, 170, 173, 175, 178 and 181 - 6/23 - Appr
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 22 15:37:43 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104F35@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'dcarlson@mit.edu'" <dcarlson@MIT.EDU>,
"'cperry@mit.edu'"
<cperry@MIT.EDU>,
"'pbaratta@mit.edu'" <pbaratta@MIT.EDU>,
"'jcollins@mit.edu'" <jcollins@MIT.EDU>, C-Zone <C-Zone@MIT.EDU>,
Billy Homeyer <whomeyer@PLANT.MIT.EDU>,
Gerry Desmond
<gdesmond@PLANT.MIT.EDU>,
"'patdixon@mit.edu'" <patdixon@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'rm-shutdown@mit.edu'"
<rm-shutdown@MIT.EDU>
Date: Thu, 22 Jun 2000 15:35:00 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: dcarlson@mit.edu; cperry@mit.edu; pbaratta@mit.edu;
> jcollins@mit.edu; C-Zone; Billy Homeyer; Gerry Desmond; patdixon@mit.edu
> Cc: shutdown@plant.mit.edu; shutdowns@mit.edu; rm-shutdown@mit.edu
> Subject: Bldg. 1 - 151, 153, 163, 170, 173, 175, 178 and 181 - 6/23 -
> Approved Shutdown
>
>
The following approved chilled Water shutdown for Bldg. 1 - 151, 153, 163,
170, 173, 175, 178 and 181 on Friday, June 23 is for your information.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 1 - 151, 153, 163, 170, 173, 175, 178 and 181
> Date: 6/24/00
> Day: Friday
> Time: 7:30 AM - 2:30 PM
> System: Chilled Water supply and return
> Duration: 8 hours
> Reason:
> Tie in new re-routed 3" chillwater supply and return in Room 1-150.
>
> Effect:
> Loss of chilled water (air conditioning) in the above listed rooms during
> the shutdown period.
>
>