[51230] in Hotline Meeting
Bldg. 54 - 6/30 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 22 14:38:00 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104F30@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'politano@mit.edu'" <politano@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'schdule@mit.edu'" <schdule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 22 Jun 2000 14:35:15 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: politano@mit.edu; shutdowns@mit.edu; schdule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 54 - 6/30 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 54 on Friday, June 30
is for your review and comment. Would you please let me know whether this
does or does not meet with your approval.
Thanks John,
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 54
> Date: 6/30/00
> Day: Friday
> Time: 8 AM - 1 PM
> System: Pump 4 and 5 perimeter induction units. Perimeter water
> circulation for boost cooling or heating depending on system needs.
> Duration: 5 hours
> Reason:
> Replacement of control valves for control of tempreature of system.
> (Chilled Water/heating hot water).
>
> Effect:
> Perimeter air flow still available but temperatures will be higher for
> loss of extra cooling.
>
>