Bldg. 8 - 3/4 - Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Feb 25 12:12:27 1999
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'ccarey@mit.edu'" <ccarey@MIT.EDU>,
"'carolr@mit.edu'" <carolr@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 25 Feb 1999 12:08:31 -0500
> To: schedule@mit.edu; shutdowns@mit.edu; ccarey@mit.edu;
> carolr@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - 3/4 - Shutdown Request
>
>
The following shutdown request for Bldg. 8 on 3/4 is for your review and
comment. Would you please let me know whether this does or does not meet
with your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 8
> Date: 3/4/99
> Day: Thursday
> Time: 6 AM - 12 Noon
> System: Hot domestic water
> Duration: 6 hours
> Reason:
> To install backflow preventors.
>
> Effect:
> Loss of hot domestic water (water used in bathroom and kitchen
> faucets) during shutdown period.
>
>