RE: Bldg. E52 All Normal Electric Power Shutdown Request for 8/5

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jul 27 15:13:10 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'lhill@mit.edu'"
	 <lhill@MIT.EDU>, "'gwj@mit.edu'" <gwj@MIT.EDU>,
        "'jbkalb@mit.edu'"
	 <jbkalb@MIT.EDU>,
        "'maureen@mit.edu'" <maureen@MIT.EDU>,
        "'jessi@mit.edu'" <jessi@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, "'mwf@mit.edul'" <mwf@mit.edul>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Date: Mon, 27 Jul 1998 15:07:45 -0400

Dear Everyone in the To Column:
Would you please let me know if the above shutdown request has your
approval or not. I have been advised by the supervisor of the
Electricians that he must have a response by tomorrow (Tuesday, July 28)
prior to 2:00 PM so that he may make the proper arrangements.

Thanks very much for your assistance in this matter.

Andrea Nichols
Operations Center
8-7872

	----------
	From:  Andrea Nichols
	Sent:  Wednesday, July 22, 1998 3:31 PM
	To:  'schedule@mit.edu'; 'shutdowns@mit.edu'; 'lhill@mit.edu';
'gwj@mit.edu'; 'jbkalb@mit.edu'; 'mwf@mit.edul'; 'maureen@mit.edu'
	Cc:  Shutdown
	Subject:  Bldg. E52 All Normal Electric Power Shutdown Request
for 8/5 PM - 8/6 AM

	The following request for a shutdown for Bldg. E52 (All Normal
Electric
	Power) on 8/5 PM and 8/6 AM is for your information and comment.
Would
	you please let me know if this meets with your approval or not.

	Thank you.

	Andrea Nichols
	Operations Center
	8-7872

	> Status: Normal
	> Building: E52
	> Date: 8/5/06
	> Day: Wednesday and Thursday
	> Time: 6 PM (8/5) - 2 AM (8/6)
	> System: Normal electric power
	> Duration: 8 hours
	> Reason: 
	> To replace high voltage switchgear.
	> 
	> Effect: 
	> Loss of Power: acess controls, building power, elevators,
computers,
	> lighting; Water: chilled water (air conditioning); Air: supply
	> ventilation, supply cooling, exhaust -general and exhaust
toilet air,
	> compressed control air; Steam - condensate return  The
Emergency Power
	> will be on and one elevator will continue to run on emergency
power..
	> 
	> 