Bldg. 14S Shutdown Request for 5/21

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 5 12:06:16 1998

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'rdavies@mit.edu'" <rdavies@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'efc@mit.edu'" <efc@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Tue, 5 May 1998 12:00:19 -0400

> To: 	rdavies@mit.edu; shutdowns@mit.edu; efc@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 14S Shutdown Request for 5/21
> 
> 
The following shutdown request for Bldg. 14S on 5/21 is for your review
and comment. Would you please let me know if this has your approval or
not.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Critical
> Building: 14S
> Date: 5/21/98
> Day: Thursday
> Time: 7:00 AM - 4:00 PM
> System: Supply Ventilation
> Duration: 9 hours
> Reason: 
> Bag filter changes for Air Handlers 1, 2, 3; Supply Fan #4 and Air
> Handler 5.
> 
> Effect: 
> Loss of supply ventilation only during shutdown period. This will not
> involve supply cooling or supply heating but air that is brought in
> from the outside.
> 
> 