Bldg. 48 Shutdown Request for 4/14
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Apr 2 13:35:51 1998
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'sfrankel@mit.edu'" <sfrankel@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'istetri@deslab.mit.edu'" <istetri@deslab.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Date: Thu, 2 Apr 1998 13:33:57 -0500
> To: sfrankel@mit.edu; schedule@mit.edu; istetri@deslab.mit.edu
> Cc: shutdown@plant.mit.edu; shutdowns@mit.edu
> Subject: Bldg. 48 Shutdown Request for 4/14
>
>
The following shutdown request for Bldg. 48 on 4/14 is for your review
and comment. Would you please let me know if this has your approval or
not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
P.S. - Physical Plant selected the time and date. If you want to change
it, please feel free to do so and let me know.
Thanks again.
Andrea Nichols
> Status: Normal
> Building: 48
> Date: 4/14/98
> Day: Tuesday
> Time: Noon - 6:00 PM
> System: Hot domestic and heating hot water; supply heating; high,
> medium and low pressure steam and smokes
> Duration: 6 hours
> Reason:
> Repair steam leak in Mechanics Room
>
> Effect:
> Loss of hot domestic water (restroom sinks and kitchen faucets);
> heating hot water; supply heating (air); high, medium and low
> pressure steam; and smokes.
>
>