[38393] in Hotline Meeting
Bldg. 12 - 182, 002A, 002B, 002, 005A and 007B on 5/22 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 16 10:45:32 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jbartels@mit.edu'" <jbartels@MIT.EDU>,
"'jcentor@mit.edu'"
<jcentor@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Fri, 16 May 1997 10:46:06 -0400
To: jbartels@mit.edu; jcentor@mit.edu; shutdowns@mit.edu
Cc: shutdown@plant.mit.edu
>Subject: Bldg. 12 - 182, 002A, 002B, 002, 005A and 007B on 5/22 Shutdown
Request
The following shutdown request is for your informtion and comment. Would
you please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Status: Normal
Building: 12 - 182, 002A, 002B, 005A & 007B
Date: 5/22/97
Day: Thursday
Time: 8:00 AM - 12 Noon
System: Chilled Water
Duration: 4 hours
Reason:
>Fan Coil unit installation within 12-022 and 12-022A - to install isolation
valves serving 12-002/002A
Effect:
Loss of chilled water during shutdown period.