Requested Revised Shutdown - Bldg. NW21 - TARA,

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Nov 12 08:46:32 1996

Date: Tue, 12 Nov 1996 08:43 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, gwinn@pfc.mit.edu
X-Envelope-To: shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, gwinn@pfc.mit.edu"

The following information pertains to the requested rescheduled
shutdown for Bldg. NW21 - for 11/13. Would you please let me know if
this is acceptable or unacceptable at your earliest convenience.

Thanks very much.

  Andrea Nichols
  Operations Center
  8-7872

  Building:       NW21 - TARA, Basement & 1st floor, Computer Room, & 194
  System:         Supply Fan 1 (PM#704864); SF2 (#704865); SF3 -
                  (#710373, and SF4 (#710374)
  Date:           11/13
  Day:            Wednesday
  Time:           9:30 AM - 12:30 PM
  Duration:       3 hours (see breakdown of time down for each unit
                  below)
  Reason:         86 Filter changes as follows: SF1 and SF2 will be
                  down for 15 minutes each, others will be down for 15 minutes
                  each.

                PM#704864 located in NW21-251 MR -services TARA
                PM#704865 located in NW21-251 MR -services TARA,
                        basement and first floors
                PM#710373 located in NW21-194 RL -services research lab
                        194
                PM#710374 located in NW21-194 RL -services research lab
                        194