[33996] in Hotline Meeting
Requested Shutdown - Bldgs. W13, W15, 41, 41A, 17,
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Jul 9 13:05:47 1996
Date: Tue, 9 Jul 1996 13:02 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, hraine@MIT.EDU, schedule@MIT.EDU, ameswf@MIT.EDU,
pmccosco@MIT.EDU, mwhelan@MIT.EDU, mwf@MIT.EDU
X-Envelope-To: ameswf@mit.edu, hraine@mit.edu, mwf@mit.edu, mwhelan@mit.edu,
pmccosco@mit.edu, schedule@mit.edu, shutdowns@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, hraine@mit.edu, schedule@mit.edu, ameswf@mit.edu, pmccos
co@mit.edu, mwhelan@mit.edu, mwf@mit.edu"
The following requested shutdown is for your review and information.
Would you please let me know if this is either acceptable or
unacceptable at your earliest convenience. I can be contacted at
8-6651 or by return email.
Thanks very much.
Andrea Nichols
Operations Center
8-6651
Building: W13, W15, 41, 41A, 17, 35 and 31
System: All normal electrical power; steam will need to be
secured in affected buildings
Date: 7/26 PM - 7/27 AM
Day: Friday PM and Saturday AM
Time: 6:30 PM (7/26) - 4:30 AM (7/27)
Duration: 10 hours
Reason: To complete work started during shutdown of
7/12-13/96 (Replacment of old high voltage switch that
affects all of the above-named buildings.)
Effect: Loss of all power (access controls, bldg. power,
elevators, computers, telephones, lighting and corridors/
stairs); chilled water;(Air) supply ventilation, supply
cooling, supply heating, exhaust laboratory, exhaust
general, exhaust toilet and compressed control;(Steam) high,
medium and low pressure steam and condensate return.