Building:       2-366, 372, 266, 268, 270, 277, 168, 170, and 172.
System:         Heating Steam
Date:           2/2/96
Day:            Friday
Time:           7:00 AM - 11:00 AM
Duration:       2 Hours
Reason:         To replace control valve.
Effect:         Loss of low pressure steam.

Building:       E17 - 1st and 2nd floors
System:         Emergency Power in labs, corridors, stairs, and exit
                signs
Date:           2/6/96
Day:            Tuesday
Time:           7:00 AM - 3:00 PM
Duration:       8 Hours
Reason:         To replace faulty panel-board and circuit breakers
Effect:         There will be no emergency power,  lab power or power
                to corridors and stairs..