HI all,


I cleared these as far ias X1410 is concerned:   Jerry


B36 -- Penthouse -- Supply Fan Approx. 1 hour Start at 6am Thursday 9/15

B13 -- PM work on Fan Hood in Approx. 1 hour start 11PM Thursday 9/15

41-009 --  Power to Lab Eqpt. Approx. 2 hours Start 7am 9/15

W34 --  Domestic Hot Water 8 Hours Thursday 9/15

NW13 -- Heat and Vent PM work rooms 223, 204, 206 and 270 Thursday 9/15

E52  -- Supply Fan 1 and 3 and RF 1.30 per Fan  approx. Start 2300 on 
Thursday 9/15

E17-636 -- Fan Hood Approx. 1 Hour start at 5am Thrusday 9/15

E17 Stairwell -- Fan Supply Approx 1 hour stat at 5am Thursday 9/15

E18-557a - Hax Exhaust Hood PM work 1 hour start at 5am Thursday 9/15

E18-all --  AH6 and RF6 Svc AQ Approx 1 hour exhaust start at 3:30am 
Thursday 9/15

12-200caa, 12-056 -- Fan Supply PM Approx. 1.5 hrs start at 7:30am 
Friday 9/16

37-015 -- Fan Supply SF1 Approx 1.5 hors start at 9:15 Friday 9/16

nw14-220 affects all lights in nw13, plus compactor in nw14, approx. 2 
hrs Friday 9/16

Copies of work orders are on the bulletin borad outside my office.


                                        Thanks, Jerry
   