[6171] in Release_7.7_team

home help back first fref pref prev next nref lref last post

Release Team Agenda: Tomorrow Jan 21 @ 3:30 in W92-199

daemon@ATHENA.MIT.EDU (William Cattey)
Tue Jan 20 16:46:05 2009

Mime-Version: 1.0 (Apple Message framework v753.1)
Content-Transfer-Encoding: 7bit
Message-Id: <E93C789A-BC4C-431F-8BC1-CAA5E1A4E0B5@MIT.EDU>
Content-Type: text/plain; charset=US-ASCII; delsp=yes; format=flowed
To: release-team@MIT.EDU
From: William Cattey <wdc@MIT.EDU>
Date: Tue, 20 Jan 2009 16:44:20 -0500
X-Spam-Flag: NO
X-Spam-Score: 0.00

Our next meeting is scheduled for tomorrow, Wed Jan 21 @ 3:30 in W92-199
Some people will be arriving early to do preparatory discussions.

Agenda:

1. Questions for team to review:

     Will we re-number low gids and low uids?
	If so, what transition work is needed?

     Shall we implement the proposed merge of Debathena and Athena10?

     Future of Open Office Locker: Should we now follow what Ubuntu  
releases?
	When should we  go live with OOo 3.0?

     Should bash be the default shell for incoming students?
	If so, what transition work is needed?

     Is the Athena 10 LiveCD an appropriate substitute for an Athena  
10 VM image?

2. Re-visiting Athena 10 Kiosk mode:

     What is the scope of need?
     What do we see as the exposure?
     Who do we think needs to bless moving forward with it?
     Can Kiosk mode be limited to a few sites?
	Register
	Xcluster
	Stock answers
	Libraries

3. Punch List to Athena 10 go-live:
	Discussed Firefox defaults, and decided not to make any changes.

	Comprehensive installer:
	Bugme:
	Create debathena-thirdparty package
	ATN-1 Improved session names:
	ATN-4 Greeter cosmetics:
	ATN-9 skip_:
	ATN-10 attach/detach: Did amb take FUSE changes? Did broder update
command utilities.? What are next steps?
	ATN-11 (su in clusters): status of broder fix to sudoers.
	ATN-12 Clean up local accounts:
	ATN-13 Fix X configuration:

Target Athena 10 dates:
	Comprehensive installer ready for use by ridgway and wdc by Tue Jan 6.
	Go-live in Early Cluster two weeks (plus holiday) later Wed Jan 21.

4. Check in on IAP Patch Release and follow-through.

5. Prep for TAP



home help back first fref pref prev next nref lref last post