Status: Accomplishments and Goals for November

daemon@ATHENA.MIT.EDU (Rocklyn Clarke)
Wed Nov 29 22:52:08 2000

Date:         Wed, 29 Nov 00 22:48:56 EST
From: Rocklyn Clarke <RCLARKE@MIT.EDU>
To: Enterprise Print Delivery Team <PRINTDEL@MIT.EDU>
Message-Id:   <001129.225016.EST.RCLARKE@MIT.EDU>
Mime-Version: 1.0
Content-Type: TEXT/PLAIN; charset=US-ASCII
Content-Transfer-Encoding: 7BIT


Hi Team,

Here they are!

Rocklyn


-------------------------------------------------------------------------
Accomplishments (since 10/30/2000):
 - Worked with team to finalize Statement of work (SOW) and project
   change request (PCR) and had them submitted to Procurement and Legal
   for processing
 - Worked with Lynne Durland and FSS to set up print queues for FSS
   Suspended further work on FSS questions (including questions from
   David Rosenberg) due to pressing higher priority tasks.
 - Worked with Lynne Durland to investigate use of Java gui via ssh
   & X-Windows
 - Arranged with ASST to have LPRng installed on Pillage for testing
 - Arranged with ASST to have Kerb v5 installed on Pillage for testing
 - Arranged with ASST to have Apache installed on Pillage in support of
   web interface development and testing

Goals for the coming month:
 - Further update Enterprise Printing WBS
 - Get signed statement of work and project change request to IBM
 - Meet with R3-Admin to discuss potential changes in print queue
   request processing
 - Work with Lynne Durland to finalize IPM accounting for production
 - Modify IPM to take feeds from Moira
 - Work with ASST to get KLPR running on Plunder and Pillage
 - Determine feasibility of AIX/DCE interoperability with MIT Kerberos
 - Test initial IPM Web Interface design from IBM
 - Set up IPM for production work.