Remaining Tasks from Today's Board Work

daemon@ATHENA.MIT.EDU (David F Lambert)
Mon Nov 6 14:16:33 2000

Message-Id: <10011061917.AA20532@MIT.EDU>
Date:         Mon, 06 Nov 00 14:14:29 EST
From: David F Lambert <LAMBERT@MITVMA.MIT.Edu>
To: Enterprise Printing Delivery Project Team <printdel@MIT.EDU>

Team,

Here's the board work with remaining tasks, responsible team member
and target due dates.  Corrections, etc. please.

MEB   1/31  produce final delivery project report
REC  11/20  implement SSH & X Windows to secure op & sys admin clients
REC   Jody  implement klpd in IPM
REC    Dan  ensure SoW work is completed ASAP
LED    Dan  move CAO's HP8100 to IPM
LED    Dan  move DOST's HP8100 to IPM
LED  12/20  provide DOST training & documentation
L&M  12/20  provide BLT training & documentation
DFL  11/30  resolve IPM AAST service issue
MEB   1/31  rollout announcement (desktop access & general announcement)
REC    Dan  implement IPM web server
DFL  11/27  resolve output delivery services to be provided
LED    Dan  secure 'x form' resources
CET   12/8  implement approved BM
C&R   12/8  implement automated accounting system
DFL   12/1  ensure disaster recovery is in place
D&C   11/9  upgrade IPM license for more printers
LED   11/9  provide Admissions testing
LED  11/15  provide Alumni testing
LED   11/1  provide SIS testing
REC  12/30  implement automated moira/IPM feeds
DFL   12/1  develop plan to support IPM impact printing
LED   12/1  implement appropriate header & trailer pages

N up testing was deemed to be post project work.  Items with names
in the date field require input from those folks.  Note: the IPM license
upgrade is not needed for project completion.