Remaining Tasks from Today's Board Work
daemon@ATHENA.MIT.EDU (David F Lambert)
Mon Nov 6 14:16:33 2000
Message-Id: <10011061917.AA20532@MIT.EDU>
Date: Mon, 06 Nov 00 14:14:29 EST
From: David F Lambert <LAMBERT@MITVMA.MIT.Edu>
To: Enterprise Printing Delivery Project Team <printdel@MIT.EDU>
Team,
Here's the board work with remaining tasks, responsible team member
and target due dates. Corrections, etc. please.
MEB 1/31 produce final delivery project report
REC 11/20 implement SSH & X Windows to secure op & sys admin clients
REC Jody implement klpd in IPM
REC Dan ensure SoW work is completed ASAP
LED Dan move CAO's HP8100 to IPM
LED Dan move DOST's HP8100 to IPM
LED 12/20 provide DOST training & documentation
L&M 12/20 provide BLT training & documentation
DFL 11/30 resolve IPM AAST service issue
MEB 1/31 rollout announcement (desktop access & general announcement)
REC Dan implement IPM web server
DFL 11/27 resolve output delivery services to be provided
LED Dan secure 'x form' resources
CET 12/8 implement approved BM
C&R 12/8 implement automated accounting system
DFL 12/1 ensure disaster recovery is in place
D&C 11/9 upgrade IPM license for more printers
LED 11/9 provide Admissions testing
LED 11/15 provide Alumni testing
LED 11/1 provide SIS testing
REC 12/30 implement automated moira/IPM feeds
DFL 12/1 develop plan to support IPM impact printing
LED 12/1 implement appropriate header & trailer pages
N up testing was deemed to be post project work. Items with names
in the date field require input from those folks. Note: the IPM license
upgrade is not needed for project completion.