[248] in Enterprise Print Delivery Team

home help back first fref pref prev next nref lref last post

Prep Notes for Tomorrow's Meeting

daemon@ATHENA.MIT.EDU (David F. Lambert)
Thu May 25 15:06:30 2000

Message-Id: <10005251906.AA05531@MIT.EDU>
Date:         Thu, 25 May 00 15:03:55 EDT
From: "David F. Lambert" <LAMBERT@MITVMA.MIT.Edu>
To: "Rocklyn E. Clarke" <rclarke@MITVMA.MIT.EDU>,
        Lynne Durland <durland@MIT.EDU>
Cc: Enterprise Printing Delivery Project Team <printdel@MIT.EDU>

Rocklyn & Lynne,

Please review and provide corrections, additions, etc. by 5pm today.
Thanks a bunch for the work this morning!

-Dave

Discussion points for the 5/26/2000 Print Delivery meeting

1) Installation of new PSF/VM release when GA
   Desired Outcomes:
   - buy-in and commitment to install the new release of PSF/VM when
     it's GA (not the beta release)
   - identification of installation staffing resources
   Project & Operational Benefits:
   - helps with the plans to eliminate the E19 channel extension
   - easier sharing of 3160(s) between VM & IPM
   - could drive the E19 3160 from Comdisco's hotsite reducing
     hotsite costs and providing improved business continuity services
   - could potentially save purchase and maintenance costs associated
     with the channel adapter on the second 3160 (timing issue)

2) IPM Support
   Desired Outcomes:
   - identify team & staff to support IPM
   - move I/T Service forward on resolving the issue of the
     organizational model for supporting administrative and "system"
     applications
   Project & Operational Benefits:
   - agreement on the future support of IPM

3) 3827 to 3160 Migration
   Desired Outcomes:
   - agreement the migration will occur
   - agreement on the funding source
   - agreement on the timeframe
   - agreement on the staff resources to be used
   Project & Operational Benefits:
   - significant cost savings
   - full redundancy between W91 and E19
   - encourages the completion of the forms conversion work which
     will allow us to fulfill our current business continuity
     commitments
   - aligns with a project goal to ease the transition of printing
     from the legacy environment to the new services by sharing
     print engines
   - the 3160 is better sized for the current workload

4) AIX & Server Support
   Desired Outcomes:
   - clarify remaining service requirements including a quick
     run through of ASST's SLA list
     (see: http://windsurf.mit.edu/ASOP/whats_it_buy.html)
   - obtain agreement to support AIX

5) Rollout
   Desired Outcomes:
   - clearer and broader understanding of the rollout plans and schedule
   7/1 Target Date (some are a stretch)
   - complete business plan (startup funding, ongoing funding, cost
     allocation, support plan, service plan, disaster recovery plan)
   - IPM up & running
   - E19 HP8100 managed by IPM
   Post 7/1
   - move GL monthly statements to Postscript & IPM
   - resolve secured access method
   - resolve desktop access method
   - evaluate moving the SAP desktop printers to IPM from APS
   - use the 3160(s) by IPM
   - review options for moving to network attached impact printers
   - resolve the move to MICR based check printing (probably part
     of Payroll Delivery)

Notes will not be included in the email to RAR, Karen, etc...

Notes: - Rocklyn will address the people "backup" issue
       - Lynne to mention "other" resources as needed (aka Art)
       - review Pete's SLA list at the following URL before the meeting
         http://windsurf.mit.edu/ASOP/whats_it_buy.html

home help back first fref pref prev next nref lref last post